CLOMR Application for Proposed Flood Control Improvements
How to sequence the analysis, filing, and ESA work for approval.

A CLOMR application for proposed flood control improvements is a sequence of engineering and regulatory decisions. Keeping the project on schedule and in compliance requires the hydraulic analysis, application record, environmental documentation, and agency reviews to advance in the right order, with a post-construction map revision planned from the outset.
What a CLOMR is and what it is not
A Conditional Letter of Map Revision is FEMA’s written opinion that a proposed project would meet National Flood Insurance Program standards if built as proposed. It does not revise the official Flood Insurance Rate Map. A Letter of Map Revision makes that change after construction and modifies the FIRM and FIS report to reflect completed work. Where a CLOMR is required, the local floodplain permit cannot be issued until approval.
Both CLOMRs and LOMRs are MT-2 revision submittals, distinct from MT-1 amendments such as LOMA and LOMR-F. Indiana DNR’s no-rise guidance identifies two paths for projects in FEMA-mapped floodways, either demonstrating no rise through certification or proceeding through the CLOMR/LOMR sequence. These paths are not interchangeable forms of approval. A no-rise certification documents the absence of a rise, while a CLOMR evaluates a proposed change against NFIP standards. Because the CLOMR remains conditional on construction as proposed, the post-construction LOMR is mandatory.
When a CLOMR is required versus when a no-rise certification is enough
The first decision is the applicable flood zone and whether a mapped floodway exists. The threshold changes with that regulatory setting. In Zone AE with a mapped floodway, any increase in base flood elevation beyond 0.00 ft requires a CLOMR. FEMA’s BLE and LOMRs guidance cites 44 CFR 60.3(d)(3), which requires communities to prohibit floodway encroachments unless analysis demonstrates no increase in flood levels. The engineer must therefore check whether the project achieves absolute zero rise before relying on certification.
In Zone AE without a mapped floodway, a CLOMR is required when the project increases BFE more than 1.0 ft, while the community monitors cumulative effects below that threshold. In Zone A, where no BFEs are shown, an increase greater than 1.0 ft at any point requires a CLOMR. Pre-project and proposed-project analysis remains necessary for community permitting in Zone A regardless of that trigger. Minnesota DNR’s LOMR Guide identifies the thresholds and cautions that local standards can be more restrictive.
The local reviewer must therefore have a say in the final decision. Denver’s 30% floodplain review for the South Platte River Trail project, 2026-CIP-0000074, states that even confirmed no-rise will likely require a CLOMR because of hydraulic complexity and overlapping corridor projects. The same review notes that a BFE drop greater than 0.3 ft may allow the CLOMR to be waived, but a LOMR remains required.
The hydrologic and hydraulic analysis that must be in hand before the application is filed
The application package is the output of the hydrologic and hydraulic analysis. Model selection must precede the engineering computations. Kentucky’s CLOMR/LOMR presentation instructs applicants to establish that FEMA approves the model before beginning, because an unapproved tool creates rework that cannot be resolved through the forms. HEC-RAS, built and maintained by the USACE Hydrologic Engineering Center, is free, FEMA-recognized, and standard for CLOMR floodway and BFE analysis.
The pre-project model comes first and must show ground conditions as they are now, even if they differ from historical conditions or those used for the effective FIRM. Base Level Engineering skeleton models may support pre-project conditions in Zone A and Zone AE without a floodway. Their role narrows in mapped floodway settings. In floodway Zone AE, BLE terrain may be used to update cross-section data or show conditions upstream and downstream, but a full pre-project model is still needed. The proposed-project model must then isolate the project’s flood-level changes from other influences, because the comparison between conditions is the technical core of the application.
The analysis produces hydrologic computations, digital model files, a certified topographic work map with floodplain and floodway delineations, and an annotated FIRM showing project changes. Denver’s review also calls for water surface profiles that show 10-, 100-, and 500-year events on all profiles and cross-sections, plus a BFE comparison table that labels all bridges and includes upstream and downstream bridge cross-sections. Concurrent work requires agreement about which projects belong in each modeled condition. Independent QA/QC by a second modeler is standard for a sealed CLOMR submittal, because a rejected submission or challenged floodway can cost weeks and weaken the firm’s credibility with the reviewer.
Assembling the MT-2 application package
The filing route should be established during scoping, before the package is assembled. MT-2 requests may go through FEMA’s Online LOMC tool or by mail to the LOMC Clearinghouse in Alexandria, Virginia, except where a Cooperating Technical Partner or LOMR Review Partner processes applications directly. Routing is not merely an administrative detail. Using the federal online route in a partner jurisdiction creates delays. Kentucky became a FEMA LOMR Review Partner on January 1, 2024, and processes MT-2 applications in-state, while FEMA continues to handle MT-1 applications.
Once the analysis is complete, the MT-2 package brings its results together with the project narrative and required certifications. Form 1 names the project, the community it affects, and the revision being requested. The narrative explains the work and its objectives, while the computations, model files, certified work map, and annotated FIRM document its effects. All data require certification by a registered professional engineer or licensed surveyor. Missing or unsigned components are the most common cause of rejection for incompleteness at first review.
The applicant, certifying engineer, and an official from each affected community must sign Form 1. A missing community signature is a common completeness failure. Plans also require attention independent of the hydraulic report. Denver’s review requires a PE seal and signature on all plans showing floodplain or floodway work, with plan sets separated by construction phase so the permit covers only plans corresponding to the hydraulic model under review.
ESA compliance as a hidden critical-path item
FEMA will not issue a CLOMR until compliance with species protection requirements is documented. An otherwise complete application can remain pending because the ESA record is unfinished, making environmental documentation a separate prerequisite that must be resolved before approval. The project team therefore should initiate this work concurrently with H&H analysis at project initiation.
The ESA process typically involves Section 7 consultation with the U.S. Fish and Wildlife Service or NOAA Fisheries, depending on the species. The time it takes does not depend on FEMA’s review clock. Faster hydraulic analysis cannot accelerate that separate process. Riparian corridors, anadromous fish habitat, and listed species critical habitat present the greatest exposure, while the location of flood control improvements in or near waterways makes early evaluation relevant to almost every CLOMR project. Responsibility for obtaining the documentation cannot be deferred to FEMA’s technical review.
What happens during FEMA's review and how to manage the comment rounds
Denver’s review uses 12 to 24 months from initial submittal to FEMA approval as the planning range and directs teams to budget time and funds accordingly. A nine-month minimum and at least two comment rounds are the least teams should expect, and the schedule should allow for more time. Kentucky’s presentation explains that the reviewer has a fixed period for each submittal and that the clock restarts with resubmittal. Once FEMA deems the package adequate, it has 90 days to issue the CLOMR or provide preliminary revised flood map panels for review and comment.
Managing that process requires separating completeness corrections from technical rework. Missing documents, unsigned forms, unsplit plan sets, and absent bridge labels in BFE tables can be resolved quickly when the record is organized. Model calibration problems, inadequate cross-section coverage, and gaps in floodway encroachment analysis require H&H revisions and are the main drivers of repeated comment rounds. Responsive resubmittals and organized document control help keep corrections from becoming avoidable delays.
In LRP and CTP jurisdictions, the state agency performs technical review before the application goes to FEMA. Kentucky’s presentation identifies local KDOW contacts who can discuss prospective applications, requirements, and the review process in advance. Those discussions can reduce the first-round comment load. Because the local permit depends on CLOMR issuance, an additional review round extends an administrative task and defers construction.
Multi-agency coordination and local floodplain permitting running in parallel
FEMA review is the longest thread, but it is not the only one. Local permitting, state review, and coordination with concurrent projects must proceed in parallel, and gaps in those efforts can hold the CLOMR even after FEMA is satisfied. All proposed work in a regulatory floodplain requires a local floodplain permit. The CLOMR does not replace that permit, and community signature on Form 1 is necessary before CLOMR issuance.
The South Platte project shows why early local review affects design. Denver requires the floodplain development permit submittal at an early design phase because technical comments can change the proposed work. Waiting until late design leaves redesign as the response. For projects with hydraulic analyses, the initial submittal bypasses the standard permitting portal and goes directly to the local floodplain management group. The reviewer then directs when the project should transition to formal permitting.
The same coordination determines the scope of the hydraulic model. Denver flags the need to resolve which concurrent projects must be added to which model condition as work progresses along the corridor. That decision belongs early in local coordination. Minnesota’s guide references state statutes and administrative regulations governing floodway delineation and flood control measures independently of federal requirements, illustrating why teams working across states cannot treat federal thresholds as the full standard.
The post-construction LOMR obligation and what a deficient no-rise finding costs
The project schedule should allow time to submit the LOMR within six months of completion. More precisely, 44 CFR 65.3 sets the deadline at six months after the date the information becomes available. Minnesota’s guide and Kentucky’s presentation identify that requirement.
The LOMR requires an as-built survey sealed by a professional surveyor, and the design model must be updated to as-built conditions. Any divergence between design and construction requires representation and reanalysis. Kentucky’s presentation identifies a BFE decrease of at least 0.1 ft as a trigger for a FIRM update, so an analysis that appeared adequate as a no-rise finding does not necessarily eliminate a post-construction LOMR obligation.
A deficient no-rise or encroachment analysis discovered during LOMR review results in a formal violation. The community must reduce the impacts on water surface elevation or the floodway and work more closely with FEMA Headquarters and the Regional Office. QA/QC at both stages is therefore risk management for the project, the firm, and the community. Indiana’s guidance describes the consequence of leaving a violation unresolved. At the extreme, community probation or suspension from the NFIP can follow, and suspension prevents floodplain properties from obtaining NFIP flood insurance required for structures with federally backed mortgages.