A riverine LOMR clears review only when every document agrees.

· 9 min read
Cover illustration for “LOMR Submittal Package Preparation for Riverine Projects”
Floodplain Studies · November 13, 2026 · 9 min read · 1,948 words

A complete riverine LOMR submittal depends on agreement among the H&H analyses, MT-2 forms, certified work maps, and annotated flood maps. Sound engineering alone does not secure approval. Each part must show the same conditions, methods, and results, and the records of community concurrence and notification must complete the case for approval. That coordination separates a review-ready package from a costly revision cycle.

What a LOMR is and when a riverine project requires one

A Letter of Map Revision, or LOMR, officially revises a community’s effective FIRM and FIS without republishing those documents. Its determination letter attaches annotated maps, profiles, and tables that supersede the published information for the revision area. A LOMR records as-built or existing conditions, while proposed projects must first go through the CLOMR pathway.

FEMA’s BLE and LOMRs guidance identifies the obligation under 44 CFR 65.3 to submit technical data within six months after construction when physical changes affect flooding conditions. Relevant changes include bridges, culverts, channelization, fill, and grading near a flooding source shown on the FIRM. Preconstruction approval depends on the flood zone. A BFE increase above 0.0 ft in Zone AE with a designated floodway, or above 1.0 ft in Zone AE without a floodway, requires CLOMR approval before construction. That review also establishes an accepted methodology that can expedite the eventual LOMR.

The complete MT-2 package and what each component must contain

The project narrative establishes the reason for the request, the scope of work, and changes since the effective study date. It describes the hydrologic and hydraulic methods and identifies whether the project is proposed or as-built. The narrative gives the reviewer an orientation. Its description must correspond to the analyses and conditions documented throughout the submission.

MT-2 Form 1 records community information, affected flood zones, the flooding source, the reason for the request, and required signatures. Form 2 documents riverine hydrology and hydraulics. It must identify the submitted hydraulic models and, for HEC-RAS, the names of the plans used. Form 3 covers riverine structures, including new bridges and culverts, structures that have changed, and revised analyses of structures already modeled in the effective FIRM and FIS. Existing bridges and culverts belong on that form only when they are being updated.

The analytical record includes hydrologic and hydraulic computations with their digital supporting files. The mapping record serves a different purpose. It includes a certified topographic work map, an annotated FIRM, and annotated FIS profiles and tables showing the requested revisions. Where they apply, proposed or as-built plans show the physical work. The package also includes the fee, community concurrence, property owner notification, applicable floodway notices and state coordination, and endangered species compliance documentation where required.

What the hydrologic analysis must actually document, and when new hydrology is required

The choice between effective discharges and new hydrology determines the scope of the entire package. New hydrology requires revision of the full modeling and mapping dataset, including replacement of flow values. That decision therefore belongs at the start. New analysis is required when effective flows do not exist, as in Zone A areas or unstudied streams, or when watershed changes make effective flows unreasonable. New analysis is also required when there are longer gaging records, better rainfall data, better methods, or errors in the effective study.

The significance of the resulting discharges also requires consideration. A small difference in the numbers alone is not enough to call for a full hydrology revision. The applicant should consider revising effective hydrology when the new discharges are statistically different from the effective values. The revised method must be as good as or better than the effective method, with explicit justification for a downgrade. In the method hierarchy, gage statistical analysis using Bulletin 17C comes before rainfall-runoff modeling and regression equations, though USGS regression equations are also accepted for use nationwide.

The digital record must document basin mapping and drainage delineation, land use and soils, and curve number calculations sourced from NRCS WSS and USGS NLCD. NOAA’s National Weather Service Precipitation Frequency Data Server is the source to use first for rainfall depths. The supporting files must also show the precipitation, unit hydrographs, and routing methods used. A Summary of Discharges Table must collate steady flow data points into official peak discharge values for the effective recurrence storms. These records explain how the submitted flows were developed.

Indiana DNR’s review team flags selection of “New Hydrology” in Form 2 Section A when the analysis actually uses effective discharges. That selection creates an expectation for a new coordinated discharge curve and steady flow data points that the package will not contain. The resulting deficiency reaches into the hydraulic review. Even complete hydrologic documentation cannot compensate for an incorrectly configured hydraulic model.

Hydraulic modeling requirements, software compliance, and what the model files must contain

Even with correct hydraulic results, the package can have incomplete files, inputs that lack support, or an unsupported software version. The digital model must show where every input came from, the datum, the model version, and what changed between plans. Those changes must be traceable through the submission. Otherwise, the reviewer cannot reconcile the narrative’s account of the analysis with the actual model configurations.

The software requirement is a separate completeness test. The accepted HEC-RAS versions identified in the supplied modeling guidance are 3.1.1, 4.1.0, 5, and 6.2.1. Legacy tools such as HEC-2 are no longer accepted, and an unsupported version produces a deficiency. The files submitted for a LOMR compare existing or as-built post-project conditions with the pre-project baseline. A CLOMR needs separate pre-project and proposed post-project plans to show how much the project would change the flood level.

The supporting record must explain cross-section geometry sources and methods, bridge and culvert data, Manning’s n sources and justification, ineffective flow areas, and upstream and downstream model limits. The comparison of pre-project and post-project conditions must show how the project meets the BFE increase threshold that applies, which depends in Zone AE on whether there is a floodway. Base Level Engineering models may be used as a pre-project starting point in Zone A and Zone AE. But in Zone AE, BLE terrain can only add to the project-area cross-section data, and the post-project model must show the actual proposed or as-built ground conditions, which BLE alone cannot provide.

Certified work maps: what they must show and how they differ from the annotated FIRM

The certified work map proves the relationship between modeled flood boundaries and the ground. It is a topographic base showing proposed or as-built floodplain boundaries, the regulatory floodway, and cross-section locations tied to the hydraulic model. It must bear a licensed professional engineer’s or surveyor’s seal. The annotated FIRM has a different function. It shows how the effective panel will change if FEMA approves the revision.

The annotated panel must identify its number and effective date, affected flood zones, the flooding source, revised BFEs, and revised boundary locations. Those entries must match what is in the model and work map. A boundary mismatch exposes why both documents are necessary. For example, an annotated FIRM could place a revised boundary where the certified work map’s contours cannot support it at the modeled elevation. Preparing the documents together allows that discrepancy to be resolved before review.

Denver DOTI’s January 1, 2026 floodplain permit requirements require drawings showing floodplain boundaries to state the FIRM panel number and effective date. The FIS record must also remain consistent. Its annotated profiles and tables must show the updated BFEs at every cross-section that is affected. Revising the FIRM while omitting those corresponding annotations leaves the package incomplete.

The community concurrence and notification requirements that engineers most often underestimate

Community concurrence and property owner notification are separate requirements under 44 CFR 65.4. Form 1 requires the signature of the CEO or legally designated CEO of every affected community. A city planner, county surveyor, or city engineer does not satisfy that requirement simply by holding a technical or planning position.

The corporate limits on the affected FIRM panel show which communities are affected. If those boundaries are in question, the submission must include an official corporate limits map or annexation agreement. Each affected community must provide its own concurrence. For projects crossing jurisdictional boundaries, the lesson is to initiate coordination early and include signature collection in the schedule. Treating concurrence as a final assembly task leaves a regulatory dependency unresolved after the engineering is complete.

The package must have separate records of property owner notification. The MT-2 form instructions have sample notification templates. State coordination can add further requirements for floodway revisions under delegation programs, including an IDNR-OWR floodway permit and floodway revision concurrence in Illinois. Indiana DNR participates in the FEMA LOMR Review Partners Program, with processing temporarily handled by Focus Revision Partners (FOCUS) because of grant funding constraints. Endangered species compliance documentation is also required where listed species may be present, so it cannot be omitted merely because the hydraulic analysis is complete.

Why incomplete submittals are so costly and how the review clock actually works

FEMA’s review window begins with receipt of a complete application. An incompleteness return resets that window and adds an equivalent delay, affecting floodplain permits, construction schedules, and financing tied to LOMR issuance. A missing signature or unreconciled map can therefore have consequences well beyond the effort needed to correct it.

An approved CLOMR has already subjected the methodology, community concurrences, and technical approach to review, allowing the post-construction LOMR to proceed on an expedited basis. It does not replace complete as-built documentation. Rather, it prevents those foundational questions from first appearing after the work is built and the project needs a final map revision.

For firms handling multiple LOMRs, preventable returns also consume staff time reconstructing submissions, coordinating signatures again, and managing client expectations. These costs accumulate across the project workload. These deficiencies can arise even when the modeling is correct because they stem from how the work is documented and coordinated. That makes them good candidates for checks in an internal QA process. The useful final review therefore checks that every file is present and cross-checks the package’s relationships.

A pre-submittal QA checklist approach that catches the most common deficiencies

A structured review against the MT-2 checklist provides a direct way to improve first-submittal approval rates. The review should begin with Form 1 signatories for every affected community and the documentation for property owner notification. State coordination records and endangered species compliance must also be addressed where applicable. These checks establish the procedural foundation of the request. They should be complete before the package is released.

The technical review should check the plan names and file names in Form 2 directly against the model files in the submission. The “New Hydrology” selection must match the actual analysis, and new hydrology must include the Summary of Discharges Table and steady flow data points. Software acceptance requires its own check. The mapping review should then check that the annotated FIRM boundaries match the certified work map geometry and that the FIS profiles and tables cover every cross-section that is affected.

AI tools with knowledge of MT-2 requirements can assist with these comparisons and with reviewing narrative methods against the analysis performed. They can also support assembly by extracting hydrologic inputs from GIS and LiDAR datasets, formatting supporting files, and cross-referencing panels against model outputs. A useful implementation fits existing HEC-RAS outputs, Civil 3D geometry, GIS datasets, and Bluebeam markup workflows rather than adding a separate export-and-reformat process.

Professional accountability remains with the engineering firm. A licensed professional engineer must review and stamp every AI-assisted output in a licensed engineering submittal before it is released. Faster assembly does not transfer responsibility for the technical content or reduce the standard of care.

Sources

  1. City and County of Denver Department of Transportation & Infrastructure
  2. September 13, 2024 Improving LOMRs How to get Approval on the First Submittal
  3. BLE and Letters of Map Revisions (LOMRs)
  4. Technical Requirements of a Letter of Map Revision Request
  5. Instructions for MT-2 Forms 1
  6. wa INAFSM 2025 Presentation.

More in Floodplain Studies